So sick of Silver Line schedule slips

My least favorite genre of local transportation story, by an overwhelming margin, is reports of delays in the second phase of Metro’s Silver Line to Dulles Airport and beyond. Over the past few months, I’ve let myself grow optimistic that this wait for a one-seat international-airport ride would end–and then this week served up a new round of gut-punch news about the project’s long-anticipated entry into revenue service.

Thursday, Washington Metropolitan Area Transportation Authority general manager Paul Wiedefeld used the agency’s board meeting to announce a new problem: incorrectly sealed joint boots connecting third rails to their power supply. It’s sufficiently irritating that these cable-connector assemblies–a basic part of the system that you can easily identify from a train, given that they look like giant orange hair dryers–were not installed right, pushing the extension’s opening into, maybe, July.

But it’s worse that Metro and the Metropolitan Washington Airports Authority, the agency overseeing the construction, apparently knew about this snafu for months but did not see fit to loop in the taxpaying public. To put this more directly: When WMATA and MWAA posted presentations earlier this month about Silver Line progress that didn’t mention this hangup, they lied.

And this development follows a long series of dashed deadline hopes.

In 2014, months after the first phase of the Silver Line had opened, this expansion was projected to open in 2018. A year later, extensive design changes had pushed that timeframe out to sometime in 2020. That estimate held through discoveries in 2018 and 2019 of such problems as defective concrete panels, incorrectly installed railroad ties and flaws in fixes for those concrete panels. But then issues with the train-control system found in 2020 yielded a revised estimate of 2021 that then evaporated as fixes for them dragged on into the summer of 2021.

MWAA declaring “substantial completion” for the Silver Line’s tracks and stations in November, followed by it reaching the same milestone in December for the extension’s rail yard, was supposed to put this extension officially in the home stretch. Instead, these two agencies have found new ways to prolong the punch-list work needed before Metro can take control of the line and then, after some 90 days of its own testing, open the faregates.

I am among the less-inconvenienced stakeholders. I don’t commute to Reston or Herndon and only lose an extra 15 or 20 minutes and $5 on each trip to IAD by having to transfer to MWAA’s Silver Line Express bus at the Wiehle-Reston East Metro station–not that every time I’m waiting for that bus, I don’t think that a completed Silver Line could have already whisked me to the airport.

But the larger picture is that $2.778 billion worth of infrastructure continues to sit idle while MWAA and WMATA point to the other party (or the Washington Metrorail Safety Commission, which must provide a separate sign-off) as the reason for the latest delay. I don’t perceive any urgency at either agency’s leadership to put this asset into service–although at this point I mostly blame Metro, since I see the same feckless lack of initiative in the transit agency’s prolonged inability to get its 7000-series trains back into service.

It’s a disgraceful failure of project management all around, and only one thing eases the embarrassment factor for my city: the far more horrific cost and schedule overruns afflicting New York’s transit projects.

Advertisement

3 thoughts on “So sick of Silver Line schedule slips

  1. I live DC and I’ve been working out at Dulles since 1993. So I’ve been waiting for over thirty years for it to open! CAN YOU IMAGINE MY PAIN?

  2. Pingback: Weekly output: AT&T and Verizon C-band progress, Gen Z online habits, lunar LTE, connected TVs vs. streaming media players, NFL Sunday Ticket, warnings of Russian and Chinese hacking, electronics recycling | Rob Pegoraro

  3. Pingback: A ride decades in the making: Metro from Dulles | Rob Pegoraro

What do you think?

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.